Posted by Stefany on Oct 13, 2025 at 03:57 AM

The Benefits Realization Framework section states:

1. It was identified in the OBC that existing schools and universities play a major role in the success or otherwise of the Pittville

project. A strategy for Learning Provider engagement is to be prepared.

2. A senior manager within the Local Education Authority is ultimately responsible for benefits realization.

Which 2 statements apply to these entries?

Suggested Answer: B, C

Get Premium Better-Business-Cases-Practitioner Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
30 comments · newest first
CH
Chi 8 months ago
I feel confused. Too many options! What’s the best approach?
LI
Ling 8 months ago
D is interesting. Project managers should oversee benefits.
GE
Georgene 8 months ago
I’m leaning towards B. Schools shouldn’t be solely responsible.
BA
Barbra 9 months ago
I agree, but E seems valid too. No need to change entry 2.
BE
Bethanie 9 months ago
No change to entry 2, seems appropriate as is.
CA
Carri 9 months ago
Wait, a senior manager is responsible? That seems odd.
NO
Noah 9 months ago
I think schools should have a bigger role in benefits delivery.
KI
Kimbery 9 months ago
Totally agree, it should be revisited in the FBC.
BR
Brynn 9 months ago
Entry 1 needs to be confirmed in the OBC.
GE
Gennie 10 months ago
Wait, is the Local Education Authority responsible for the Pittville project? I thought this was about benefits realization, not a geography quiz!
BE
Berry 10 months ago
Hmm, I wonder if the Pittville project involves building a giant slide or something. That would be a pretty sweet benefit!
BE
Bernardo 10 months ago
B) is just silly. Schools and universities won't be responsible for delivering the benefits.
DE
Dean 10 months ago
A) is a bit off. The strategy should be confirmed in the FBC, not the OBC.
KA
Katlyn 10 months ago
E) is the way to go. The senior manager in the Local Education Authority is the right person for benefits realization.
KA
Karan 10 months ago
I think C is the best choice. Reaffirming is crucial.
TU
Tuyet 11 months ago
D) is wrong. The project manager is not responsible for benefits realization.
CL
Clarence 11 months ago
C) is the correct answer. The strategy for benefits realization should be revisited and re-affirmed in the FBC.
RO
Roselle 11 months ago
A feels right. The strategy should be confirmed in the OBC.
JO
Josephine 11 months ago
I feel pretty confident about this one. Entry 1 is talking about the importance of engaging with learning providers, which should have been addressed in the OBC. So option A, amending entry 1, seems like the right choice. And for entry 2, the question is clear that a senior manager in the Local Education Authority is responsible, not the project manager.
LU
Luisa 12 months ago
Hmm, this is tricky. I'm leaning towards option C - no change to entry 1, because the strategy for benefits realization should be revisited and re-affirmed in the FBC. That seems to make the most sense to me based on the information given. But I'll need to double-check the other options to be sure.
CE
Ceola 12 months ago
Okay, let me take a look. I think the key here is understanding the difference between the OBC (Outline Business Case) and the FBC (Full Business Case). The question is asking about the Benefits Realization Framework, so I'll need to consider how that fits into the overall project planning process.
HO
Honey 1 year ago
I'm a bit confused by this question. It seems like we need to analyze these two entries and decide which statements apply to them. I'll need to carefully read through the options and think about how they relate to the information provided.
HA
Hannah 7 months ago
↳ replying to Honey
I believe entry 2 is fine as it is. No need to change it.
OC
Ocie 7 months ago
↳ replying to Honey
Yeah, entry 1 seems crucial for the strategy.
TA
Tawny 7 months ago
↳ replying to Honey
I think we should focus on entry 1 first.
LA
Lavera 11 months ago
↳ replying to Honey
I agree, but what about entry 2? Is it really appropriate?
ED
Edelmira 1 year ago
I thought the project manager was responsible for benefits realization, so maybe we should consider option D for entry 2.
TE
Teri 1 year ago
I'm a bit confused about entry 1; I feel like it should be amended, but I can't recall the exact reason why.
CA
Carlota 1 year ago
I remember a practice question where we had to identify roles in benefits realization, and it seems like option E could be correct for entry 2.
RO
Robt 1 year ago
I think option C makes sense since the strategy should be revisited in the FBC, but I'm not entirely sure.
0/2000 characters

Save Cancel