APM Exam APM-PMQ Topic 3 Question 19 Discussion

Actual exam question for APM's APM-PMQ exam
Question #: 19
Topic #: 3
[All APM-PMQ Questions]

Which of the activities below would provide final assurance of a project?

Show Suggested Answer Hide Answer
Suggested Answer: C

Product testing ensures the deliverables meet the intended specifications and are ready for deployment, which is the final assurance step before project closure.


Contribute your Thoughts:

Hubert
3 days ago
Testing the product for sure. That's the only way to really confirm everything is working properly and the project is a success. Seems like the obvious choice to me.
upvoted 0 times
...
Jade
9 days ago
Hmm, I'm a bit unsure on this one. I was thinking the allocation and approval of the project budget might be the key to final assurance, but I could be wrong. Guess I'll have to think it through more carefully.
upvoted 0 times
...
Stephaine
14 days ago
I think testing of the product would be the best option to provide final assurance of the project. That's where you really validate that everything is working as expected.
upvoted 0 times
...