Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

APM Exam APM-PMQ Topic 2 Question 17 Discussion

Actual exam question for APM's APM-PMQ exam
Question #: 17
Topic #: 2
[All APM-PMQ Questions]

You are the project manager on a construction project for a client in the defence sector. The client has strict regulatory requirements and expects a high level of control and governance throughout the project. Which life cycle would be most suitable?

Show Suggested Answer Hide Answer
Suggested Answer: D

The Linear (or Waterfall) lifecycle is the most suitable for projects that require high levels of governance, control, and strict adherence to regulatory requirements.

Applicability: Linear project management focuses on predefined stages (e.g., requirements, design, implementation) that align with regulatory needs.

Advantages: It allows detailed documentation, structured review processes, and adherence to pre-approved plans, ensuring compliance with defence sector standards.

Alternative Options: Iterative and incremental approaches are less appropriate due to the less structured nature of deliverable evolution in these methods.


Contribute your Thoughts:

Jean
1 months ago
Definitely gotta go with D) Linear. Strict regulations and high control? That's a no-brainer, my friend.
upvoted 0 times
...

Save Cancel