Which of the following would be considered as the main purpose of a project management plan?
B) To enable agreement between the project sponsor and project manager with regard to project budget, resource requirements and timescale.
A) To provide a documented account of the outcomes of the planning process.
C) To provide A. record of how the project was planned, for archiving in the organisation's lessons learned.
D) To identify and record the projects intended financial spend over the period of project delivery.