Project success criteria are best defined as:
A) the qualitative or quantitative measures by which the success of the project is judged.
B) the factors that, when present in the project are most conducive to a successful outcome.
C) the measures that establish if project activities are ahead or behind schedule.
D) the activities or elements of the project which are considered to be critical to success