APM Exam APM-PFQ Topic 2 Question 16 Discussion

Actual exam question for APM's APM-PFQ exam
Question #: 16
Topic #: 2
[All APM-PFQ Questions]

A member of your team has described being involved in a risk event. Which one of the following would best describe such an event?

Show Suggested Answer Hide Answer
Suggested Answer: D