According to the Theory of Constraints, which of the following statements is true?
D) Use of Drum-Buffer-Rope includes communication from the bottleneck to the Gateway workcenter
A) A buffer of inventory should always be maintained after the bottleneck.
B) Constraints always exist in a factory
C) Work centers feeding bottlenecks should operate at peak utilization to ensure WIP availability at all times.