An increase in the scrap allowance in an assembled item will result in which of the following consequences?

Suggested Answer: C

Scrap allowance is a percentage or quantity of material that is expected to be lost or wasted during the production process. Scrap allowance is usually applied to the component items in a bill of materials (BOM), which is a document that lists the materials, quantities, and relationships required to produce an end item. An increase in the scrap allowance in an assembled item will result in replanning of the component items in material requirements planning (MRP), which is a system that calculates the timing and quantity of materials and resources needed to meet the production plan. Replanning of the component items in MRP means that the system will adjust the planned order releases, order quantities, and due dates of the component items to account for the increased scrap allowance. Replanning of the component items in MRP will ensure that enough material is available to meet the demand for the assembled item, and to avoid shortages or excess inventory.


Get Premium CPIM-Part-2 Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
12 comments · newest first
EL
Elenora 27 days ago
C makes sense too. MRP would need to be updated for new quantities.
LE
Lenny 1 month ago
I feel B is also a possibility. The BOM might need adjustments.
RO
Rosina 1 month ago
I think A is correct. More scrap means higher costs.
PA
Paola 1 month ago
D) Increased lead time? That sounds about right.
CH
Christoper 2 months ago
C) Replanning in MRP is definitely a must with more scrap.
IZ
Izetta 2 months ago
Wait, does it really change the BOM quantity? Not so sure about that.
HE
Hermila 2 months ago
Totally agree, more scrap means higher costs!
RO
Rozella 2 months ago
A) An increase in the component items' cost is likely.
JI
Jillian 2 months ago
I feel like replanning in MRP is definitely a possibility with changes in scrap allowance, so option C might be the right answer.
JE
Jenelle 2 months ago
I'm a bit confused about how scrap allowances impact lead time. Could it really increase the planned lead time like option D suggests?
LA
Lashawnda 3 months ago
I remember a practice question about BOM changes, so maybe option B could be correct if the scrap allowance affects the quantities needed.
LI
Lilli 3 months ago
I think an increase in the scrap allowance might lead to an increase in the component items' cost, but I'm not entirely sure.
0/2000 characters

Save Cancel