APICS CPIM-MPR Exam - Topic 4 Question 62 Discussion
In a capacity-constrained situation, which of the following actions is best to take if marketing wants to increase production of a master schedule item?
B) Increase production of the item, and decrease production of another item.
A) Increase production of the item, but do not make any other changes.
C) Increase production of the item, and change the production plan.
D) If the item is within the demand time fence, let the computer make the change automatically.