APICS Exam CPIM-MPR Topic 4 Question 29 Discussion

Actual exam question for APICS's Certified in Production and Inventory Management - Master Planning of Resources exam
Question #: 29
Topic #: 4
[All Certified in Production and Inventory Management - Master Planning of Resources Questions]

The question below is based on the following information:

A company has chosen to execute a level production plan. What is the production rate per period?

Show Suggested Answer Hide Answer
Suggested Answer: A