APICS CPIM-MPR Exam - Topic 2 Question 90 Discussion

Actual exam question for APICS's CPIM-MPR exam
Question #: 90
Topic #: 2
[All CPIM-MPR Questions]

Which of the following factors typically has the largest effect on the schedule developed by an advanced production scheduling (APS) system?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

0/2000 characters
Zack
3 months ago
Wow, I never thought about capacity data being that influential!
upvoted 0 times
...
Tracey
3 months ago
Wait, are we sure about B? Performance measures seem less critical.
upvoted 0 times
...
Felicia
3 months ago
A is important too, past due work can really mess things up.
upvoted 0 times
...
Junita
4 months ago
I disagree, I’d say D has the biggest impact with master schedule priorities.
upvoted 0 times
...
Omer
4 months ago
I think it's definitely C, precision of capacity data is crucial.
upvoted 0 times
...
Elli
4 months ago
I’m a bit confused about this one; I thought performance measures were crucial, but now I'm not sure how they compare to the other options.
upvoted 0 times
...
Royce
4 months ago
I feel like the amount of past due work could have a significant impact too, but I can't recall if it outweighs the others.
upvoted 0 times
...
Nu
4 months ago
I remember a practice question that emphasized the importance of priorities in the master schedule, so I might lean towards option D.
upvoted 0 times
...
Zana
5 months ago
I think the precision of the capacity data might be really important, but I'm not entirely sure if it's the largest factor.
upvoted 0 times
...
Leota
5 months ago
I'm a bit confused on this one. I'll need to think through the different factors and how they influence the APS schedule.
upvoted 0 times
...
Kanisha
5 months ago
The priorities of the master schedule items seem like they would have the biggest impact. The APS system has to balance all those competing priorities.
upvoted 0 times
...
Emelda
5 months ago
Hmm, I'm not totally sure about this one. I'll have to review my notes on APS systems and the different inputs that affect the schedule.
upvoted 0 times
...
Marti
5 months ago
This seems like a tricky question. I'll need to think carefully about the key factors that influence APS scheduling.
upvoted 0 times
...
Youlanda
5 months ago
I'm pretty confident I know the answer to this. The precision of the capacity data is crucial for an APS system to develop an accurate, feasible schedule.
upvoted 0 times
...
Trinidad
5 months ago
This looks like a straightforward question about project configuration. I'll need to carefully review the details provided and think through the differences between the current OPS project and the new change request requirements.
upvoted 0 times
...
Sharee
5 months ago
Okay, I think I know how to do this. The question is asking me to apply the Jump & Turn animation effect to the 3D model on slide 3.
upvoted 0 times
...
Dwight
5 months ago
I'm a little confused by this question. The options cover a range of things related to clients, but I'm not sure which one is the right definition of client roles. I'll have to make an educated guess on this one.
upvoted 0 times
...
Rashad
5 months ago
I'm a bit unsure on this one. I know creatinine is related to kidney function, but I can't quite recall the specific normal range. I'll have to make an educated guess.
upvoted 0 times
...
Darnell
5 months ago
Disk quotas seem like the obvious choice here. That's the most direct way to control and limit disk usage on the server.
upvoted 0 times
...
Pamella
2 years ago
Haha, I bet the person who wrote this question was an accountant. They always think everything comes down to the numbers!
upvoted 0 times
Avery
2 years ago
D) Priorities of the master schedule items
upvoted 0 times
...
Yong
2 years ago
C) Precision of the capacity data
upvoted 0 times
...
Karl
2 years ago
B) Performance measures used
upvoted 0 times
...
Jannette
2 years ago
A) Amount of past due work
upvoted 0 times
...
...
Louvenia
2 years ago
I think performance measures used can also greatly impact the schedule.
upvoted 0 times
...
Alesia
2 years ago
I believe the priorities of the master schedule items play a bigger role in the APS system.
upvoted 0 times
...
Lindy
2 years ago
Hmm, I'm torn between B and C. Both performance measures and capacity data seem like they'd heavily influence the APS system's output.
upvoted 0 times
Verdell
2 years ago
Precision of the capacity data
upvoted 0 times
...
Tammi
2 years ago
Performance measures used
upvoted 0 times
...
...
Adolph
2 years ago
D seems like the right answer to me. The priorities of the master schedule items should have the biggest impact on the final schedule.
upvoted 0 times
Quentin
2 years ago
But don't you think the precision of the capacity data also plays a significant role?
upvoted 0 times
...
Yun
2 years ago
I agree, the priorities of the master schedule items are crucial for the schedule.
upvoted 0 times
...
...
Blondell
2 years ago
I agree with Nickie, having accurate capacity data is crucial for the schedule.
upvoted 0 times
...
Nickie
2 years ago
I think the precision of the capacity data is the most important factor.
upvoted 0 times
...
Lisha
2 years ago
I think the answer is C. The precision of the capacity data is crucial for an APS system to accurately schedule production.
upvoted 0 times
Desirae
2 years ago
I believe the amount of past due work can also play a significant role in the schedule developed by an APS system.
upvoted 0 times
...
Tresa
2 years ago
I think it could also be the priorities of the master schedule items that have a big effect on the schedule.
upvoted 0 times
...
Karma
2 years ago
I agree, the precision of the capacity data is definitely important for an APS system.
upvoted 0 times
...
...

Save Cancel