APICS CPIM-MPR Exam - Topic 2 Question 17 Discussion
Which of the following actions would most likely lead to an achievable master production schedule?
A) Minimizing changes in periods before the demand time fence
B) Keeping safety stock for key subassemblies
C) Limiting changes in periods after the planning time fence
D) Committing to customer requested shipment dates