Translation of a master production schedule directly into key resources results in a:
Suggested Answer: C
Get Premium CPIM-MPR Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
12 comments · newest first
LO
Louvenia
27 days ago
I lean towards C) too. It helps in understanding capacity needs before production.
MA
Madalyn
1 month ago
I feel like A) production schedule could also fit. It’s more straightforward.
BE
Beckie
1 month ago
I think it's C) rough-cut capacity plan. It makes sense for resource allocation.
LA
Launa
1 month ago
Final assembly schedule seems too specific for this.
TO
Tom
2 months ago
Wait, are we sure about that? Sounds off.
LE
Lenna
2 months ago
Totally agree, it's all about capacity planning!
HE
Helga
2 months ago
I thought it was a production schedule?
HY
Hyun
2 months ago
It's definitely a rough-cut capacity plan.
NI
Nickie
2 months ago
I’m leaning towards A) production schedule, but I remember there was some confusion about how it ties into resource planning.
SH
Sherrell
2 months ago
I feel like the final assembly schedule could be related, but it seems more specific than what the question is asking.
ST
Stephen
3 months ago
I remember we practiced a question about production schedules, but I can't recall if that was the same as a master production schedule.
RI
Richelle
3 months ago
I think the answer might be C) rough-cut capacity plan, but I'm not entirely sure. We discussed something similar in class.