APICS CPIM-MPR Exam - Topic 1 Question 61 Discussion
If the master production schedule is overstated, which of the following short-term actions is most appropriate?
D) Firm planned orders should be rescheduled.
A) The demand time fence should be moved out.
B) Lot sizes should be decreased.
C) Safety stocks should be decreased.