Question #: 43
Topic #: 2
[All CPIM-BSP Questions]

Part A is made from two Y's and one X. An order is received for 50 A's and there are 30 A's in stock. What is the net requirement for X?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

0/2000 characters
Rhea
4 months ago
This seems off, how do we know the Y's are enough?
upvoted 0 times
...
Felix
4 months ago
Just to clarify, you need 50 A's total, right?
upvoted 0 times
...
My
4 months ago
Wait, are you sure it's not 40?
upvoted 0 times
...
Nieves
4 months ago
Totally agree, it's 20!
upvoted 0 times
...
Rachael
5 months ago
The net requirement for X is 20.
upvoted 0 times
...
Georgene
5 months ago
Hmm, I'm a bit stuck on this one. I'll need to review my notes on PDM-QSK modulation to figure out the right approach.
upvoted 0 times
...
Leota
5 months ago
I'm pretty confident these two queries will get the same result. The "!=" and "NOT" operators are both used to exclude events with a status of 100, so the output should be identical. I'll make sure to test this quickly before submitting my answer.
upvoted 0 times
...
Sharika
5 months ago
Feasibility studies seem like the way to go here. That's where you'd get the detailed analysis of the technical and operational requirements for migrating the ERP system to the cloud. The other options don't seem as directly relevant to addressing the company's main concern.
upvoted 0 times
...