Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

APICS CPIM-BSP Exam - Topic 2 Question 43 Discussion

Part A is made from two Y's and one X. An order is received for 50 A's and there are 30 A's in stock. What is the net requirement for X?
A) 20
B) 40
C) 50
D) 100

APICS CPIM-BSP Exam - Topic 2 Question 43 Discussion

Actual exam question for APICS's CPIM-BSP exam
Question #: 43
Topic #: 2
[All CPIM-BSP Questions]

Part A is made from two Y's and one X. An order is received for 50 A's and there are 30 A's in stock. What is the net requirement for X?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

0/2000 characters
Rhea
10 months ago
This seems off, how do we know the Y's are enough?
upvoted 0 times
...
Felix
10 months ago
Just to clarify, you need 50 A's total, right?
upvoted 0 times
...
My
10 months ago
Wait, are you sure it's not 40?
upvoted 0 times
...
Nieves
10 months ago
Totally agree, it's 20!
upvoted 0 times
...
Rachael
11 months ago
The net requirement for X is 20.
upvoted 0 times
...
Georgene
11 months ago
Hmm, I'm a bit stuck on this one. I'll need to review my notes on PDM-QSK modulation to figure out the right approach.
upvoted 0 times
...
Leota
11 months ago
I'm pretty confident these two queries will get the same result. The "!=" and "NOT" operators are both used to exclude events with a status of 100, so the output should be identical. I'll make sure to test this quickly before submitting my answer.
upvoted 0 times
...
Sharika
11 months ago
Feasibility studies seem like the way to go here. That's where you'd get the detailed analysis of the technical and operational requirements for migrating the ERP system to the cloud. The other options don't seem as directly relevant to addressing the company's main concern.
upvoted 0 times
...

Save Cancel