[Inspection and Testing Requirements]Which of the following is the appropriate term for testing refractory that was sampled during project site installation in order to confirm that it meets specified physical property standards?
C) As-installed testing
A) Hammer testing
B) Pre-qualification testing
D) Visual testing

API-936 Exam - Topic 1 Question 23 Discussion

Actual exam question for API's API-936 exam
Question #: 23
Topic #: 1
[All API-936 Questions]

[Inspection and Testing Requirements]

Which of the following is the appropriate term for testing refractory that was sampled during project site installation in order to confirm that it meets specified physical property standards?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

0/2000 characters
Arletta
3 days ago
Really? I thought visual testing was enough.
upvoted 0 times
...
Joana
8 days ago
Wait, isn't it B) Pre-qualification testing?
upvoted 0 times
...
Paul
13 days ago
Totally agree, that sounds right!
upvoted 0 times
...
Lazaro
18 days ago
I think it's C) As-installed testing.
upvoted 0 times
...
An
24 days ago
I feel like "Visual testing" is too general for what we need here. It doesn't really confirm physical property standards, does it?
upvoted 0 times
...
Frederica
29 days ago
Hammer testing seems like it could be relevant, but I can't recall if it specifically applies to refractory materials.
upvoted 0 times
...
Twanna
1 month ago
I remember discussing "Pre-qualification testing" in class, but that was more about testing before installation, right?
upvoted 0 times
...
Jerlene
1 month ago
I think the term we're looking for might be "As-installed testing," but I'm not entirely sure. It sounds familiar from our last practice session.