U.S. Independence Day Deal! Unlock 25% OFF Today – Limited-Time Offer - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AMP CRL Exam - Topic 5 Question 6 Discussion

Which of the following estimates represents the typical cost savings of a US $100,000 project by performing it in a proactive mode instead of a reactive mode?
A) US $25,000 to US $50,000
B) US $45,000 to US $70,000
C) US $65,000 to US $90,000

AMP CRL Exam - Topic 5 Question 6 Discussion

Actual exam question for AMP's CRL exam
Question #: 6
Topic #: 5
[All CRL Questions]

Which of the following estimates represents the typical cost savings of a US $100,000 project by performing it in a proactive mode instead of a reactive mode?

Show Suggested Answer Hide Answer
Suggested Answer: A

The best answer is A because the question asks for a typical cost-saving estimate, not an extreme or best-case savings claim. In reliability engineering, proactive work reduces avoidable costs by preventing emergency labor, expedited parts, unplanned downtime, rework, collateral damage, and production disruption. However, a proactive approach does not normally remove nearly the entire project cost. A savings range of US $25,000 to US $50,000 on a US $100,000 reactive project reflects a realistic 25% to 50% cost-avoidance band. Option B may be possible in some favorable cases but is less typical. Option C is too aggressive for a general estimate because it implies that most of the project cost disappears simply by being proactive. Reactive maintenance is performed after failure and is often associated with urgent, disruptive, and expensive response work, while proactive and preventive approaches reduce the probability and impact of those failures. This aligns with the CRL emphasis on moving from reactive firefighting to proactive reliability strategy.


Contribute your Thoughts:

0/2000 characters

Currently there are no comments in this discussion, be the first to comment!


Save Cancel