As the project reaches completion, whose approval should be sought to formally close the change?
Formal closure of a change management effort requires approval from the senior sponsor. This ensures the accountable executive validates that outcomes were achieved, ownership transferred, and sustainability measures are in place. The project manager approves project closure, while the change lead and training lead execute tasks but do not have the authority to formally close. Thus, the sponsor's approval is required to ensure accountability for benefits realization.
(Reference: ACMP Standard, Process Group 5 -- Close; Activity: Seek formal sponsor approval for closure.)
Jerrod
9 hours agoTawny
6 days agoMaira
11 days agoJerry
16 days agoDarrin
21 days agoKimberely
26 days agoCherry
1 month agoBrice
1 month agoNickolas
1 month agoGilma
2 months agoNichelle
2 months agoAlysa
2 months agoDenise
2 months agoReena
2 months agoLai
2 months agoTerrilyn
3 months agoTaryn
3 months agoSkye
3 months agoKatina
3 months ago