What is a key objective of completing a change management effort?
The primary objective of closure is to transition to maintenance and sustainability activities, ensuring the change becomes part of everyday operations. ACMP explains that this involves transferring ownership to operational leaders, embedding reinforcement mechanisms, and releasing resources. Assessing capacity (B) and preparing for continuous improvement (C) are useful lessons learned, but they are not the closure objective. Revising targets (D) is a tactical step, not a closure requirement. Option A is the correct answer.
(Reference: ACMP Standard, Process Group 5 -- Close; Objective: Transition ownership to sustain adoption and benefits.)