[Process Organization]The business process owner is responsible for
B) Design, development, execution, and ongoing performance of the process.
A) Modeling, development, and ongoing execution performance of the process.
C) Configuring the business process management system (BPMS).
D) Change request forms and alignments with technical teams.

ABPMP CBPA Exam - Topic 4 Question 23 Discussion

Actual exam question for ABPMP's CBPA exam
Question #: 23
Topic #: 4
[All CBPA Questions]

[Process Organization]

The business process owner is responsible for

Show Suggested Answer Hide Answer
Suggested Answer: B