You are reporting the following Earned Value Analysis information for the project:
EV= $1,500,000
AC=$1.000,000
PV= $2,000,000
What is the status of the project?
The problem provides key metrics used in Earned Value Management (EVM):
Earned Value (EV): $1,500,000
Actual Cost (AC): $1,000,000
Planned Value (PV): $2,000,000
Key Points:
Schedule Performance Index (SPI):
SPI = EV / PV = $1,500,000 / $2,000,000 = 0.75
An SPI less than 1 indicates the project is behind schedule.
Cost Performance Index (CPI):
CPI = EV / AC = $1,500,000 / $1,000,000 = 1.5
A CPI greater than 1 indicates the project is under budget.
Conclusion: The correct answer is C. Project is behind schedule, but under budget because the SPI indicates a delay in schedule, and the CPI shows that the project is currently spending less than planned.
Jerry
7 months agoAlbert
7 months agoBrock
7 months agoBrinda
8 months agoMarjory
8 months agoMike
8 months agoJoesph
8 months agoFlo
8 months agoDaron
9 months agoYolando
9 months agoStacey
9 months agoLou
9 months agoStevie
9 months agoReed
9 months agoVal
9 months agoTamar
9 months agoOsvaldo
2 years agoRonny
2 years agoSolange
2 years agoMerilyn
2 years agoPeggy
2 years agoBrigette
2 years agoBenton
2 years agoRasheeda
2 years agoKimi
2 years agoGlory
2 years agoLong
2 years agoVenita
2 years agoFelicidad
2 years agoAn
2 years agoAja
2 years agoEliseo
2 years ago