You are reporting the following Earned Value Analysis information for the project:
EV= $1,500,000
AC=$1.000,000
PV= $2,000,000
What is the status of the project?
The problem provides key metrics used in Earned Value Management (EVM):
Earned Value (EV): $1,500,000
Actual Cost (AC): $1,000,000
Planned Value (PV): $2,000,000
Key Points:
Schedule Performance Index (SPI):
SPI = EV / PV = $1,500,000 / $2,000,000 = 0.75
An SPI less than 1 indicates the project is behind schedule.
Cost Performance Index (CPI):
CPI = EV / AC = $1,500,000 / $1,000,000 = 1.5
A CPI greater than 1 indicates the project is under budget.
Conclusion: The correct answer is C. Project is behind schedule, but under budget because the SPI indicates a delay in schedule, and the CPI shows that the project is currently spending less than planned.
Jerry
4 months agoAlbert
4 months agoBrock
4 months agoBrinda
5 months agoMarjory
5 months agoMike
5 months agoJoesph
5 months agoFlo
5 months agoDaron
6 months agoYolando
6 months agoStacey
6 months agoLou
6 months agoStevie
6 months agoReed
6 months agoVal
6 months agoTamar
6 months agoOsvaldo
2 years agoRonny
2 years agoSolange
1 year agoMerilyn
1 year agoPeggy
1 year agoBrigette
2 years agoBenton
1 year agoRasheeda
2 years agoKimi
2 years agoGlory
2 years agoLong
2 years agoVenita
2 years agoFelicidad
2 years agoAn
1 year agoAja
2 years agoEliseo
2 years ago