You are reporting the following Earned Value Analysis information for the project:
EV= $1,500,000
AC=$1.000,000
PV= $2,000,000
What is the status of the project?
The problem provides key metrics used in Earned Value Management (EVM):
Earned Value (EV): $1,500,000
Actual Cost (AC): $1,000,000
Planned Value (PV): $2,000,000
Key Points:
Schedule Performance Index (SPI):
SPI = EV / PV = $1,500,000 / $2,000,000 = 0.75
An SPI less than 1 indicates the project is behind schedule.
Cost Performance Index (CPI):
CPI = EV / AC = $1,500,000 / $1,000,000 = 1.5
A CPI greater than 1 indicates the project is under budget.
Conclusion: The correct answer is C. Project is behind schedule, but under budget because the SPI indicates a delay in schedule, and the CPI shows that the project is currently spending less than planned.
Osvaldo
11 months agoRonny
11 months agoSolange
10 months agoMerilyn
10 months agoPeggy
10 months agoBrigette
11 months agoBenton
10 months agoRasheeda
11 months agoKimi
11 months agoGlory
11 months agoLong
11 months agoVenita
11 months agoFelicidad
11 months agoAn
10 months agoAja
11 months agoEliseo
11 months ago