You are reporting the following Earned Value Analysis information for the project:
EV= $1,500,000
AC=$1.000,000
PV= $2,000,000
What is the status of the project?
The problem provides key metrics used in Earned Value Management (EVM):
Earned Value (EV): $1,500,000
Actual Cost (AC): $1,000,000
Planned Value (PV): $2,000,000
Key Points:
Schedule Performance Index (SPI):
SPI = EV / PV = $1,500,000 / $2,000,000 = 0.75
An SPI less than 1 indicates the project is behind schedule.
Cost Performance Index (CPI):
CPI = EV / AC = $1,500,000 / $1,000,000 = 1.5
A CPI greater than 1 indicates the project is under budget.
Conclusion: The correct answer is C. Project is behind schedule, but under budget because the SPI indicates a delay in schedule, and the CPI shows that the project is currently spending less than planned.
Jerry
9 months agoAlbert
9 months agoBrock
9 months agoBrinda
10 months agoMarjory
10 months agoMike
10 months agoJoesph
10 months agoFlo
10 months agoDaron
11 months agoYolando
11 months agoStacey
11 months agoLou
11 months agoStevie
11 months agoReed
11 months agoVal
11 months agoTamar
11 months agoOsvaldo
2 years agoRonny
2 years agoSolange
2 years agoMerilyn
2 years agoPeggy
2 years agoBrigette
2 years agoBenton
2 years agoRasheeda
2 years agoKimi
2 years agoGlory
2 years agoLong
2 years agoVenita
2 years agoFelicidad
2 years agoAn
2 years agoAja
2 years agoEliseo
2 years ago