Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International CCP Exam - Topic 5 Question 1 Discussion

Actual exam question for AACE International's CCP exam
Question #: 1
Topic #: 5
[All CCP Questions]

When using a fixed-price./lump-sum contract, which of the following; situations can a payment be made for the adjustment of fluctuations in the cost of of construction resources?

Show Suggested Answer Hide Answer
Suggested Answer: C

In a fixed-price/lump-sum contract, the agreed price is fixed and generally not subject to adjustment based on fluctuations in costs, unless explicitly stated in the contract terms. Payment for adjustments in construction costs due to fluctuations in resource prices or delays is typically not allowed unless there is a specific provision for such adjustments, which is rare in fixed-price contracts. Therefore, the correct answer is C. In no situation.

Top of Form

Bottom of Form


Contribute your Thoughts:

0/2000 characters
Dominic
4 months ago
No way it's C. There are always exceptions in contracts!
upvoted 0 times
...
Barrett
4 months ago
Wait, can you really adjust for costs like that? Seems odd!
upvoted 0 times
...
Tequila
4 months ago
B is a common situation, but I don't think it applies here.
upvoted 0 times
...
Britt
5 months ago
A makes sense too, but it depends on the methodology.
upvoted 0 times
...
Nu
5 months ago
I think it's D for sure. Costs outside anyone's control should be covered.
upvoted 0 times
...
Avery
5 months ago
I lean towards option C, as I recall that fixed-price contracts are meant to be firm, so adjustments might not be allowed at all.
upvoted 0 times
...
Hoa
5 months ago
I feel like option A could be a possibility since it refers to a methodology proposed at the tender stage, but I’m not confident.
upvoted 0 times
...
Lynna
5 months ago
I'm not entirely sure, but I remember a practice question that discussed how fixed-price contracts usually don’t allow for adjustments unless specified.
upvoted 0 times
...
Julene
6 months ago
I think option D might be correct because it mentions costs beyond the control of either party, which seems reasonable for adjustments.
upvoted 0 times
...
Jacklyn
6 months ago
I'm confident I know the answer to this. Option D seems to be the correct choice - adjustments can be made for changes in the cost of resources that are beyond the control of the contractor or the client.
upvoted 0 times
...
Daniel
6 months ago
Okay, I think I've got this. The key is to identify the situations where the contract allows for adjustments to the fixed price, like changes in resource costs beyond the control of either party.
upvoted 0 times
...
Elvera
6 months ago
Hmm, I'm a bit unsure about this one. I'll need to carefully review the options and think through the different scenarios where a payment adjustment might be allowed.
upvoted 0 times
...
Tom
6 months ago
This question seems straightforward, but I want to make sure I understand the key details about fixed-price/lump-sum contracts and when adjustments can be made.
upvoted 0 times
...
Santos
6 months ago
This seems like a tricky question. I'll need to think carefully about the key requirements of Industry 4.0 and how 5G's capabilities can address them.
upvoted 0 times
...
Candida
6 months ago
Hmm, I'm not too sure about the differences between OM3 and OM4 fiber optic cables. I'll need to review my notes on the core diameters to figure this one out.
upvoted 0 times
...
Veronica
1 year ago
I'll take 'Unexpected Cost Overruns' for $500, Alex. Option D is the clear winner here.
upvoted 0 times
...
Dortha
1 year ago
Ha! Good luck trying to predict construction costs these days. Option D is the only way to go if you don't want to end up broke.
upvoted 0 times
Brinda
1 year ago
D) For changes in The cost of resources beyond the control of either party
upvoted 0 times
...
Verona
1 year ago
B) For changes in construction cost 'or varied works carried out beyond the original dale of completion
upvoted 0 times
...
Annice
1 year ago
A) For changes in prices calculated in accordance with a methodology proposed by the contractor at tender stage.
upvoted 0 times
...
...
Aleisha
2 years ago
I agree with Mindy. Fluctuations in the cost of construction resources are often unpredictable, and the contract should have a provision to adjust for those changes.
upvoted 0 times
Na
1 year ago
D) For changes in The cost of resources beyond the control of either party
upvoted 0 times
...
Annelle
1 year ago
B) For changes in construction cost 'or varied works carried out beyond the original dale of completion
upvoted 0 times
...
Rasheeda
1 year ago
A) For changes in prices calculated in accordance with a methodology proposed by the contractor at tender stage.
upvoted 0 times
...
...
Mindy
2 years ago
Option D seems like the most reasonable choice. Changes in resource costs beyond the control of either party should be accounted for in a fixed-price contract.
upvoted 0 times
Nakita
1 year ago
Option D seems like the most reasonable choice. Changes in resource costs beyond the control of either party should be accounted for in a fixed-price contract.
upvoted 0 times
...
Laticia
1 year ago
D) For changes in The cost of resources beyond the control of either party
upvoted 0 times
...
Timothy
1 year ago
B) For changes in construction cost 'or varied works carried out beyond the original dale of completion
upvoted 0 times
...
Kati
1 year ago
A) For changes in prices calculated in accordance with a methodology proposed by the contractor at tender stage.
upvoted 0 times
...
...
Andrew
2 years ago
Hmm, that's a good point. But what about option D? Changes in cost of resources beyond anyone's control could also be a valid reason for adjustment.
upvoted 0 times
...
Chau
2 years ago
I disagree, I believe the answer is B. It makes sense to adjust for varied works carried out beyond the original date of completion.
upvoted 0 times
...
Andrew
2 years ago
I think the answer is A, because the contractor proposed the methodology at tender stage.
upvoted 0 times
...

Save Cancel