When using a fixed-price./lump-sum contract, which of the following; situations can a payment be made for the adjustment of fluctuations in the cost of of construction resources?
In a fixed-price/lump-sum contract, the agreed price is fixed and generally not subject to adjustment based on fluctuations in costs, unless explicitly stated in the contract terms. Payment for adjustments in construction costs due to fluctuations in resource prices or delays is typically not allowed unless there is a specific provision for such adjustments, which is rare in fixed-price contracts. Therefore, the correct answer is C. In no situation.
Top of Form
Bottom of Form
Veronica
11 months agoDortha
11 months agoBrinda
10 months agoVerona
10 months agoAnnice
10 months agoAleisha
11 months agoNa
10 months agoAnnelle
10 months agoRasheeda
10 months agoMindy
11 months agoNakita
10 months agoLaticia
10 months agoTimothy
10 months agoKati
10 months agoAndrew
11 months agoChau
11 months agoAndrew
12 months ago