Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International CCP Exam - Topic 3 Question 43 Discussion

If a project is said to be on a "fast track program/' the fast track method is:
A) Simultaneous working engineering, procurement, and construction, with appropriate overlap from each phase of work so that delays are eliminated and all the work is streamlined into a correct plan of logic/sequence and duration for all of the work
B) First completing engineering and procurement, then executing construction
C) Analyzing the project and specifying the basic approach to be used in its execution; segmenting the project into reasonable number of activities; estimating the time required to perform each activity; placing the activities in time order, considering both sequential and parallel performance
D) Revising the schedule logic to make it possible to identify constraints of faulty logic; revising the durations in the n p schedule that have been based on assumptions regarding the \hay the work would be performed; revise the resources to work multiple shifts; evaluate the use of overtime

AACE International CCP Exam - Topic 3 Question 43 Discussion

Actual exam question for AACE International's CCP exam
Question #: 43
Topic #: 3
[All CCP Questions]

If a project is said to be on a "fast track program/' the fast track method is:

Show Suggested Answer Hide Answer
Suggested Answer: A

The fast track method in project management is a technique that involves overlapping the phases of engineering, procurement, and construction. Instead of completing these phases sequentially (which is typical in traditional project management), fast tracking allows for simultaneous work on these phases with appropriate overlap. The goal is to reduce the overall project duration by eliminating delays and streamlining the work into a logical and efficient sequence. This method is often used in projects where time is a critical factor.

Option B describes a traditional sequential approach, not fast tracking.

Option C outlines the process of project scheduling and planning, which involves sequencing activities but does not address the simultaneous execution of phases.

Option D focuses on schedule revision and constraint identification, not the simultaneous execution characteristic of fast tracking.

Thus, A. Simultaneous working engineering, procurement, and construction is the correct answer.


Contribute your Thoughts:

0/2000 characters
Latrice
4 days ago
But B seems safer. Finish one phase first, then move on.
upvoted 0 times
...
Marguerita
9 days ago
I agree, A makes sense. Delays need to be avoided.
upvoted 0 times
...
Wilbert
15 days ago
I think it's A. Fast track means overlapping phases.
upvoted 0 times
...
Whitney
20 days ago
Yup, A is the way to go for efficiency!
upvoted 0 times
...
Shaun
25 days ago
A is the definition of fast track, no doubt about it.
upvoted 0 times
...
Rosina
1 month ago
Wait, can you really overlap all those phases without issues? Sounds risky!
upvoted 0 times
...
Millie
1 month ago
Totally agree, A is definitely the correct answer.
upvoted 0 times
...
Ryan
1 month ago
Fast track means doing engineering, procurement, and construction at the same time!
upvoted 0 times
...
Naomi
2 months ago
I feel like option C is about planning and sequencing, which is important, but it doesn’t really capture the essence of fast tracking like A does.
upvoted 0 times
...
Leandro
2 months ago
I’m a bit confused about the differences between options A and B. I thought fast tracking meant doing things at the same time, but B seems to suggest a more traditional approach.
upvoted 0 times
...
Terrilyn
2 months ago
I remember practicing a question similar to this, and I think option A sounds right because it emphasizes simultaneous work, which is key in fast tracking.
upvoted 0 times
...
Willodean
2 months ago
I think the fast track method involves overlapping phases, but I'm not entirely sure if it’s just about engineering and construction or if procurement is included too.
upvoted 0 times
...

Save Cancel