AACE International CCP Exam - Topic 3 Question 11 Discussion

Posted by Raymon on Sep 14, 2024 at 12:29 PM

Which of the following is NOT an advantage specific to a cost reimbursable contract?

Suggested Answer: D

In a cost reimbursable contract, the contractor is reimbursed for all allowable costs incurred during the project, plus an additional fee (which could be a fixed fee or a percentage of costs). This contract type provides several advantages but also has its limitations.

Key Points:

Advantages of Cost Reimbursable Contracts:

Simpler Proposal Evaluation: The focus is on selecting the best contractor rather than the lowest bid, making the evaluation process simpler.

Flexibility in Dealing with Changes: This contract type allows for adjustments and changes as the project progresses.

Early Start: Work can begin quickly without needing a fully defined scope since costs are reimbursed.

Owner Control:

While cost reimbursable contracts offer flexibility, they do not inherently mean that the owner controls all aspects of the work. The contractor typically manages the execution of the project, while the owner retains control over the budget and major decisions.

Conclusion: The correct answer is D. Owner controls all aspects of the work because, in cost reimbursable contracts, the contractor has significant control over how the work is performed, while the owner mainly controls costs and high-level decisions.


Get Premium CCP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
44 comments · newest first
EV
Eva 11 months ago
I think owner control is a big advantage, though.
SH
Shawnna 11 months ago
Early starts can definitely happen with these contracts.
HE
Heike 11 months ago
Wait, how is "evaluation of proposals" simpler? That sounds off.
DO
Dortha 12 months ago
Totally agree, flexibility is key!
NO
Nohemi 12 months ago
Cost reimbursable contracts are usually more flexible.
SA
Samira 1 year ago
I practiced a similar question, and I think the early start mentioned in option C is often a benefit, so maybe that's not the answer either.
RO
Rolande 1 year ago
I feel like option D could be the one that doesn't fit, as the owner doesn't control everything in a cost reimbursable contract.
MA
Mabel 1 year ago
I'm not entirely sure, but I remember that flexibility in dealing with changes is a key advantage, so it can't be the answer.
RE
Reyes 1 year ago
I think option A might be the right answer since cost reimbursable contracts usually have more complex evaluations.
VI
Vicente 1 year ago
I've got this! The owner controlling all aspects of the work is a disadvantage, not an advantage, of a cost reimbursable contract.
VA
Valentine 1 year ago
I'm a bit confused on the differences between the options. I'll have to read them over again and think it through step-by-step.
MY
Myra 1 year ago
Okay, I know the key advantages are flexibility and an early start. I just need to identify which one is not an advantage.
ER
Ernestine 1 year ago
Hmm, I'm a bit unsure about the advantages of cost reimbursable contracts. Let me think this through carefully.
LE
Leatha 1 year ago
This question seems straightforward, I think I can handle it.
TE
Terrilyn 1 year ago
This question seems straightforward, but I want to make sure I understand the key details before answering.
WI
Wilda 2 years ago
Owner controls all aspects of the work? Sounds like a recipe for a micromanager's dream. No thanks!
MA
Marion 2 years ago
↳ replying to Wilda
C) An early start can be made
PE
Penney 2 years ago
↳ replying to Wilda
B) Provides flexibility in dealing with changes
VI
Vi 2 years ago
↳ replying to Wilda
A) Evaluation of proposals are much simpler
AR
Arlie 2 years ago
Cost reimbursable contracts? More like 'cost reimbursable headaches', am I right? *chuckles*
AN
Annamaria 2 years ago
↳ replying to Arlie
C) An early start can be made
NO
Noel 2 years ago
↳ replying to Arlie
B) Provides flexibility in dealing with changes
KI
Kiley 2 years ago
↳ replying to Arlie
A) Evaluation of proposals are much simpler
RO
Rozella 2 years ago
This question is as clear as mud. I guess I'll just throw a dart and hope for the best.
LA
Lazaro 2 years ago
An early start can be made? That's a good one, but I'm not falling for it. Gotta go with A on this one.
NA
Nadine 2 years ago
↳ replying to Lazaro
Definitely not C, An early start can be made.
JE
Jennie 2 years ago
↳ replying to Lazaro
I agree, A) Evaluation of proposals are much simpler.
RA
Raylene 2 years ago
↳ replying to Lazaro
I think A is the correct answer.
AR
Arthur 2 years ago
But with a cost reimbursable contract, the owner doesn't control all aspects of the work, so D) doesn't make sense.
AL
Alfred 2 years ago
I disagree, I believe the correct answer is A) Evaluation of proposals are much simpler.
MA
Malcolm 2 years ago
Evaluation of proposals being simpler? Sounds like a trap to me. I'll go with D - owner controls all aspects of the work.
AL
Alisha 2 years ago
↳ replying to Malcolm
So, the correct answer is D - owner controls all aspects of the work.
ET
Ettie 2 years ago
↳ replying to Malcolm
I don't think that's it, C is actually an advantage of a cost reimbursable contract.
SA
Sarina 2 years ago
↳ replying to Malcolm
But what about C - an early start can be made?
KA
Karon 2 years ago
↳ replying to Malcolm
I think you're right, D does seem like the best choice.
TI
Tiera 2 years ago
↳ replying to Malcolm
I agree, the owner controlling all aspects of the work is not an advantage.
NO
Nobuko 2 years ago
↳ replying to Malcolm
Definitely not an advantage, it limits the contractor's flexibility.
GA
Galen 2 years ago
↳ replying to Malcolm
I think D is the correct answer too.
AR
Arthur 2 years ago
I think the answer is D) Owner controls all aspects of the work.
AL
Alison 2 years ago
Hmm, I thought cost reimbursable contracts were all about flexibility, but I guess the owner has a lot of control too. Interesting...
NE
Nenita 2 years ago
↳ replying to Alison
D) Owner controls all aspects of the work
LI
Lisha 2 years ago
↳ replying to Alison
C) An early start can be made
RI
Richelle 2 years ago
↳ replying to Alison
B) Provides flexibility in dealing with changes
JU
Julie 2 years ago
↳ replying to Alison
A) Evaluation of proposals are much simpler
0/2000 characters

Save Cancel