New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International CCP Exam - Topic 2 Question 15 Discussion

Actual exam question for AACE International's CCP exam
Question #: 15
Topic #: 2
[All CCP Questions]

After collecting the control information on a light rail project within an original budget of 200.0OO work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor is 60%.

After collecting the control information on a light rail project within an original budget of 200.000work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.

Is the percent complete stated by the contractor correct?

Show Suggested Answer Hide Answer
Suggested Answer: C

The problem provides key metrics used in Earned Value Management (EVM):

Earned Value (EV): $1,500,000

Actual Cost (AC): $1,000,000

Planned Value (PV): $2,000,000

Key Points:

Schedule Performance Index (SPI):

SPI = EV / PV = $1,500,000 / $2,000,000 = 0.75

An SPI less than 1 indicates the project is behind schedule.

Cost Performance Index (CPI):

CPI = EV / AC = $1,500,000 / $1,000,000 = 1.5

A CPI greater than 1 indicates the project is under budget.

Conclusion: The correct answer is C. Project is behind schedule, but under budget because the SPI indicates a delay in schedule, and the CPI shows that the project is currently spending less than planned.


Contribute your Thoughts:

0/2000 characters
Arletta
3 months ago
They’ve paid more hours than earned, that’s a red flag.
upvoted 0 times
...
Fannie
3 months ago
Wait, how did they get to 60%? Sounds off.
upvoted 0 times
...
Ardella
3 months ago
No way, it should be lower than that!
upvoted 0 times
...
Hoa
4 months ago
I thought it was 60% too, seems right.
upvoted 0 times
...
Tamekia
4 months ago
The contractor's progress is actually 52.5%.
upvoted 0 times
...
Desire
4 months ago
If I remember correctly, we should use the earned hours divided by the scheduled hours to find the percent complete. That makes me think it's not 60%.
upvoted 0 times
...
Christiane
4 months ago
I feel like the contractor's 60% might be too high, but I can't recall the exact formula to confirm it.
upvoted 0 times
...
Linwood
4 months ago
I remember a similar question where we had to calculate percent complete using earned value. I think it might be around 52.5% here.
upvoted 0 times
...
Aleta
5 months ago
I think the percent complete is based on earned hours, but I'm not sure how to calculate it exactly.
upvoted 0 times
...
Heike
5 months ago
Alright, time to put my problem-solving skills to the test. I'm confident I can figure out the right answer here, I just need to take it slow and make sure I don't miss anything.
upvoted 0 times
...
Whitley
5 months ago
This seems straightforward enough. I'll just plug the numbers into the formula for percent complete and see if I get the same 60% the contractor is reporting.
upvoted 0 times
...
Vicky
5 months ago
I'm a bit confused by all the different numbers here. I'll need to make sure I understand what each one represents before I can decide if the 60% is correct or not.
upvoted 0 times
...
Jennifer
5 months ago
Okay, let me think this through step-by-step. The original budget was 200,000 work hours, and 100,000 have been scheduled so far. With 105,000 work hours earned and 110,000 paid, I think the contractor's 60% claim might be off.
upvoted 0 times
...
Ashton
5 months ago
Hmm, this looks like a tricky one. I'll need to carefully review the information provided and do the calculations to determine the correct percent complete.
upvoted 0 times
...
Tu
10 months ago
Hmm, the contractor's statement of 60% progress doesn't add up. Let me crunch the numbers... Ah, I see it now - the correct percent complete is 55%. Looks like the contractor is trying to pull a fast one on the client. Better double-check those figures, my friend!
upvoted 0 times
...
Ciara
10 months ago
Haha, the contractor must be living in a different reality to claim 60% progress. According to the numbers, it's clearly 52.5% complete. Someone needs to give this contractor a reality check before the client catches on!
upvoted 0 times
Isaiah
8 months ago
They better fix their numbers before the progress meeting.
upvoted 0 times
...
Francis
8 months ago
The client won't be happy when they find out the truth.
upvoted 0 times
...
France
8 months ago
Contractor needs to get their math right, it's definitely 52.5% complete.
upvoted 0 times
...
...
Brent
10 months ago
The contractor's progress statement of 60% seems off. Given the information, the correct percent complete should be 50%. The scheduled work hours are 100,000, but the actual work hours earned are only 105,000, which is less than the 110,000 work hours paid. This suggests the project is behind schedule.
upvoted 0 times
Ben
8 months ago
C: So, the project is actually behind schedule then.
upvoted 0 times
...
Carli
9 months ago
B: I agree, it should be 50% based on the information provided.
upvoted 0 times
...
Kathrine
9 months ago
A: The contractor's progress statement of 60% is incorrect.
upvoted 0 times
...
...
Terrilyn
11 months ago
I think the contractor's stated progress of 60% is incorrect. Based on the information provided, the percent complete should be 52.5%. The work hours scheduled to date are 100,000, while the work hours earned are 105,000. This means the project is only 52.5% complete, not 60%.
upvoted 0 times
Joaquin
10 months ago
I think the contractor needs to reevaluate their progress calculation, it should be 52.5% not 60%.
upvoted 0 times
...
Andree
10 months ago
I agree, the percent complete should be 52.5% based on the work hours scheduled and earned.
upvoted 0 times
...
...
Clorinda
11 months ago
I believe the correct answer is B) No, it should be 50.0% because the earned work hours are higher than the scheduled work hours.
upvoted 0 times
...
Alishia
11 months ago
I agree, it should be lower than 60%.
upvoted 0 times
...
Telma
11 months ago
I think the contractor's progress is incorrect.
upvoted 0 times
...

Save Cancel