After collecting the control information on a light rail project within an original budget of 200.0OO work hours, the construction contractor is ready for their monthly progress meeting with the client.
A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor is 60%.
After collecting the control information on a light rail project within an original budget of 200.000work hours, the construction contractor is ready for their monthly progress meeting with the client.
A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.
Is the percent complete stated by the contractor correct?
The problem provides key metrics used in Earned Value Management (EVM):
Earned Value (EV): $1,500,000
Actual Cost (AC): $1,000,000
Planned Value (PV): $2,000,000
Key Points:
Schedule Performance Index (SPI):
SPI = EV / PV = $1,500,000 / $2,000,000 = 0.75
An SPI less than 1 indicates the project is behind schedule.
Cost Performance Index (CPI):
CPI = EV / AC = $1,500,000 / $1,000,000 = 1.5
A CPI greater than 1 indicates the project is under budget.
Conclusion: The correct answer is C. Project is behind schedule, but under budget because the SPI indicates a delay in schedule, and the CPI shows that the project is currently spending less than planned.
Arletta
9 months agoFannie
9 months agoArdella
9 months agoHoa
10 months agoTamekia
10 months agoDesire
10 months agoChristiane
10 months agoLinwood
10 months agoAleta
11 months agoHeike
11 months agoWhitley
11 months agoVicky
11 months agoJennifer
11 months agoAshton
11 months agoTu
1 year agoCiara
1 year agoIsaiah
1 year agoFrancis
1 year agoFrance
1 year agoBrent
1 year agoBen
1 year agoCarli
1 year agoKathrine
1 year agoTerrilyn
1 year agoJoaquin
1 year agoAndree
1 year agoClorinda
1 year agoAlishia
1 year agoTelma
1 year ago