Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International Exam CCP Topic 2 Question 15 Discussion

Actual exam question for AACE International's CCP exam
Question #: 15
Topic #: 2
[All CCP Questions]

After collecting the control information on a light rail project within an original budget of 200.0OO work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor is 60%.

After collecting the control information on a light rail project within an original budget of 200.000work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.

Is the percent complete stated by the contractor correct?

Show Suggested Answer Hide Answer
Suggested Answer: C

The problem provides key metrics used in Earned Value Management (EVM):

Earned Value (EV): $1,500,000

Actual Cost (AC): $1,000,000

Planned Value (PV): $2,000,000

Key Points:

Schedule Performance Index (SPI):

SPI = EV / PV = $1,500,000 / $2,000,000 = 0.75

An SPI less than 1 indicates the project is behind schedule.

Cost Performance Index (CPI):

CPI = EV / AC = $1,500,000 / $1,000,000 = 1.5

A CPI greater than 1 indicates the project is under budget.

Conclusion: The correct answer is C. Project is behind schedule, but under budget because the SPI indicates a delay in schedule, and the CPI shows that the project is currently spending less than planned.


Contribute your Thoughts:

Tu
20 days ago
Hmm, the contractor's statement of 60% progress doesn't add up. Let me crunch the numbers... Ah, I see it now - the correct percent complete is 55%. Looks like the contractor is trying to pull a fast one on the client. Better double-check those figures, my friend!
upvoted 0 times
...
Ciara
21 days ago
Haha, the contractor must be living in a different reality to claim 60% progress. According to the numbers, it's clearly 52.5% complete. Someone needs to give this contractor a reality check before the client catches on!
upvoted 0 times
...
Brent
29 days ago
The contractor's progress statement of 60% seems off. Given the information, the correct percent complete should be 50%. The scheduled work hours are 100,000, but the actual work hours earned are only 105,000, which is less than the 110,000 work hours paid. This suggests the project is behind schedule.
upvoted 0 times
Kathrine
8 days ago
A: The contractor's progress statement of 60% is incorrect.
upvoted 0 times
...
...
Terrilyn
2 months ago
I think the contractor's stated progress of 60% is incorrect. Based on the information provided, the percent complete should be 52.5%. The work hours scheduled to date are 100,000, while the work hours earned are 105,000. This means the project is only 52.5% complete, not 60%.
upvoted 0 times
Joaquin
1 months ago
I think the contractor needs to reevaluate their progress calculation, it should be 52.5% not 60%.
upvoted 0 times
...
Andree
1 months ago
I agree, the percent complete should be 52.5% based on the work hours scheduled and earned.
upvoted 0 times
...
...
Clorinda
2 months ago
I believe the correct answer is B) No, it should be 50.0% because the earned work hours are higher than the scheduled work hours.
upvoted 0 times
...
Alishia
2 months ago
I agree, it should be lower than 60%.
upvoted 0 times
...
Telma
2 months ago
I think the contractor's progress is incorrect.
upvoted 0 times
...

Save Cancel