AACE International Exam CCP Topic 1 Question 8 Discussion

Actual exam question for AACE International's CCP exam
Question #: 8
Topic #: 1
[All CCP Questions]

Which of the following best describes the three key participants for projects that are executed under a three-party contractual relationship?

Show Suggested Answer Hide Answer
Suggested Answer: C

In construction and project management, a three-party contractual relationship typically involves three key participants: the Owner, the Engineer, and the Contractor.

Key Points:

Owner:

The entity that funds and owns the project. The owner defines the project scope, objectives, and requirements and is the ultimate decision-maker.

Engineer:

Often referred to as the 'Designer' or 'Consultant,' the engineer is responsible for the technical design and specifications of the project. They ensure the project is constructed according to the owner's requirements and standards.

Contractor:

The party responsible for executing the construction work. The contractor follows the design provided by the engineer and delivers the project within the agreed terms of the contract.

Conclusion: The correct answer is C. Owner, engineer, contractor because these three parties are central to the execution and management of construction projects under a three-party contractual arrangement.


Contribute your Thoughts:

Gracia
10 months ago
Haha, this is a tricky one! I'm going with Option C, though. The owner, engineer, and contractor - that's the holy trinity of construction, right?
upvoted 0 times
Leah
9 months ago
Definitely, they each play a crucial role in the project's execution.
upvoted 0 times
...
Abel
10 months ago
I agree, those three are essential for a successful project.
upvoted 0 times
...
Buck
10 months ago
I think Option C is correct. The owner, engineer, and contractor are the key participants.
upvoted 0 times
...
...
Elbert
10 months ago
I'm not sure, but I think A) Contracting officer, contractor, and contractor project manager could also be correct.
upvoted 0 times
...
Norah
10 months ago
I agree with Corazon, because the owner, engineer, and contractor are the key participants in project execution.
upvoted 0 times
...
Arlette
11 months ago
Ah, the classic three-party contract question! Option C is the way to go, my friends. The owner, engineer, and contractor - that's the holy trinity of project management!
upvoted 0 times
...
Theresia
11 months ago
I'm torn between Options C and D, but I think C is the better choice. The three key roles make more sense for a three-party contract.
upvoted 0 times
Francine
9 months ago
It's important to consider the specific responsibilities of each key participant in the project.
upvoted 0 times
...
Sherman
9 months ago
Option D doesn't quite fit the typical roles involved in a three-party contract.
upvoted 0 times
...
Elise
9 months ago
The roles of owner, engineer, and contractor align well with the key participants in such projects.
upvoted 0 times
...
Luisa
9 months ago
I agree, Option C seems to be the best choice for a three-party contractual relationship.
upvoted 0 times
...
Hyun
10 months ago
Yes, Option C makes the most sense. The owner, engineer, and contractor are the key participants in projects executed under a three-party contract.
upvoted 0 times
...
Pamela
10 months ago
I think Option C is the most logical choice as well. It aligns with the typical roles involved in a three-party contractual relationship.
upvoted 0 times
...
Lorean
10 months ago
I agree, Option C seems to be the best choice. The roles of owner, engineer, and contractor make sense for a three-party contract.
upvoted 0 times
...
...
Marylyn
11 months ago
Option C seems to be the correct answer. The three key participants are the owner, engineer, and contractor, as they are typically involved in a three-party contractual relationship.
upvoted 0 times
Justa
10 months ago
Definitely, it's important for all three parties to work together effectively.
upvoted 0 times
...
Deeanna
10 months ago
That makes sense, they each play a crucial role in the project.
upvoted 0 times
...
Jesusa
10 months ago
Yes, the owner, engineer, and contractor are the key participants in a three-party contractual relationship.
upvoted 0 times
...
Gertude
11 months ago
I think option C is the correct answer.
upvoted 0 times
...
...
Corazon
11 months ago
I think the answer is C) Owner, engineer, contractor.