Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International CCP Exam - Topic 1 Question 42 Discussion

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.Which of the following percent complete measurement techniques is best suited for long-term non-production accounts (such as overhead accounts)?
A) Ratio/level of effort
B) Start/finish
C) Units completed
D) Incremental milestone

AACE International CCP Exam - Topic 1 Question 42 Discussion

Actual exam question for AACE International's CCP exam
Question #: 42
Topic #: 1
[All CCP Questions]

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Which of the following percent complete measurement techniques is best suited for long-term non-production accounts (such as overhead accounts)?

Show Suggested Answer Hide Answer
Suggested Answer: A

For long-term, non-production accounts (such as overhead accounts), the Ratio/level of effort measurement technique is best suited. This technique is used to measure work that doesn't directly produce deliverables but contributes indirectly to project progress, such as administrative tasks, support activities, and management efforts. The level of effort is typically spread evenly over a time period and is often calculated based on the passage of time rather than specific work units or milestones.


Contribute your Thoughts:

0/2000 characters
I seem to recall that for projects with unique technology, using a ratio/level of effort might help in estimating costs better, but I need to double-check that.
upvoted 0 times
...
Buddy
5 days ago
I'm a bit confused about the differences between start/finish and units completed. I feel like both could apply in some way, but I can't decide.
upvoted 0 times
...
Precious
10 days ago
I remember practicing a question like this, and I think the incremental milestone method could work well for tracking progress over the long term.
upvoted 0 times
...
Mitsue
15 days ago
I think the ratio/level of effort might be the best choice since it relates to ongoing overhead costs, but I'm not entirely sure.
upvoted 0 times
...

Save Cancel