Develop a CPM method considering the below tasks and logical relationships. Use this information to answer the related questions.
What is the late finish date of activity 50?
To determine the late finish date of Activity 50 using the CPM method, you would consider the latest finish times of its successors. The path through the project network would lead to the calculation that the latest possible time that Activity 50 can finish without delaying the project is Day 37. Therefore, the correct answer is D. Day 37.