In a fixed price contract the:
In a fixed-price/lump-sum contract, the agreed price is fixed and generally not subject to adjustment based on fluctuations in costs, unless explicitly stated in the contract terms. Payment for adjustments in construction costs due to fluctuations in resource prices or delays is typically not allowed unless there is a specific provision for such adjustments, which is rare in fixed-price contracts. Therefore, the correct answer is C. In no situation.
Top of Form
Bottom of Form
Devorah
3 months agoDanica
1 months agoSheron
2 months agoAlexia
2 months agoKiley
3 months agoPok
3 months agoKarl
1 months agoMattie
2 months agoChristiane
2 months agoLorrie
2 months agoAllene
3 months agoChristiane
2 months agoLashaun
2 months agoNoel
2 months agoAudria
3 months agoBarrett
2 months agoJeannetta
3 months agoYun
3 months agoCeleste
4 months agoMaxima
4 months agoAlex
4 months ago