In a fixed price contract the:
In a fixed-price/lump-sum contract, the agreed price is fixed and generally not subject to adjustment based on fluctuations in costs, unless explicitly stated in the contract terms. Payment for adjustments in construction costs due to fluctuations in resource prices or delays is typically not allowed unless there is a specific provision for such adjustments, which is rare in fixed-price contracts. Therefore, the correct answer is C. In no situation.
Top of Form
Bottom of Form
Devorah
10 days agoKiley
12 days agoPok
14 days agoAllene
18 days agoAudria
1 months agoBarrett
3 days agoJeannetta
21 days agoYun
27 days agoCeleste
2 months agoMaxima
2 months agoAlex
2 months ago